Proposal template

Construction proposal template

A free construction proposal template for general contractors and builders, in seven sections: what the homeowners told you on the site visit, the job in stages with a schedule, what's included, allowances and change orders, one fixed price paid as the work is done, and the next steps. With a filled-in residential example. Read it here or get it as a Word file and a PDF.

Michael Koper
By Michael Koper, founder of Nusii Updated
The construction proposal template: the cover and the investment page, a $168,000 primary suite addition in eight stages
Get the Word + PDF
On this page
  1. What to include
  2. The template
  3. A filled-in example
  4. How to write one
  5. See it as your client will
  6. What to charge
  7. The email to send
  8. After you send it
  9. Word and PDF
  10. Questions

What should a construction proposal include?

A construction proposal is the document a contractor sends after the site visit to win a building job: what the client needs, how you'll build it and when, what the price covers and what it doesn't, how much it costs and how it's paid, and how to say yes. For a general contractor's residential job it should have these seven parts:

  1. 1 IntroductionThe job, the fixed price, the finish date and how payments work, in three sentences.
  2. 2 What we heardWhat the clients told you, what you measured, and what it's worth against moving.
  3. 3 How we'll build itThe job in stages, week by week, with the inspections and how you run the site.
  4. 4 Additions we've built for families like yoursTwo similar jobs you finished, with photos, a reference and your license.
  5. 5 What's includedIncluded and not included, allowances, change orders, your insurance and warranty.
  6. 6 InvestmentOne fixed price in stages, each paid when that stage is finished and inspected.
  7. 7 Next stepsHow to accept, the contract and deposit, the permit, the start date and your call.

The construction proposal template, section by section

Copy one section or the whole thing. Under each section: what it's for, and one thing we've learned from the proposals sent with Nusii.

[Yellow] you write [Green] Nusii fills in when you send it

1. Introduction

The whole job in three sentences, with the fixed price, the finish date and how payments work, then who you are. Both homeowners read it, and the one who wasn't at the site visit reads it first. Working on your own? Write "I" instead of "we".

Hi [Client first name],

Thanks for walking us through the house on [date of the site visit]. You told us that [the problem in one sentence, in the client's words, such as "we've outgrown the house, but we love the street and the kids' school, and we don't want to move"].

In short: we build a [24-by-16-foot primary suite with a walk-in closet and a full bathroom] at the [back] of your house for a fixed price of [$168,000], ready to move into by [June 1, 2027]. You pay as each stage is finished and inspected, never ahead of the work, and the price only changes if you sign for a change first.

[Your company] is a licensed general contractor in [city], license [number]. We've built [number] additions [in this area] since [year], with our own [carpenters] and the same [plumber and electrician] on every job.

[Your name]
[Your role], [Your company]

About a third of first looks at proposals sent with Nusii happen on a phone (32.5%, July to September 2026). That's why the price, the finish date and the payment rule fit on the first screen, before anyone scrolls.

2. What we heard

Shows you listened on the site visit, says what you measured, and puts the addition next to the alternative the clients are weighing, which is usually moving. Only you can write this one: replace the examples with what your clients said, in their words.

Each point below answers something you told us. If we got anything wrong, tell us before you accept and we'll fix it.

  • You said [the kids share a room, and you two have the smallest bedroom in the house]. We'll build [a primary suite of your own at the back, so each child gets a room].
  • You said [you can't live with months of dust and workers in the kitchen]. We'll build the addition from the outside and open the wall into the house only once it's weathertight, behind a sealed dust wall, [in the last two weeks].
  • You said [the last contractor's price went up every week]. We'll hold one fixed price. Only two things change it: a change you ask for and sign, and something hidden in the ground or the walls, which we show you and price in writing before we touch it.

What we measured: [the site, with numbers, such as "a flat back yard with 32 feet to the property line, a 1960s ranch house on a crawlspace, a 100-amp electrical panel, and the gas and sewer lines along the north side"].

What stays: [what won't change, such as "the oak tree, the patio and the kitchen"].

What success looks like: [a result you can both check, such as "you sleep in the new suite by June 1, 2027, every inspection is signed off, and the final price is $168,000 plus only the changes you signed"].

What it's worth: you told us [a four-bedroom house in the same school district costs about $150,000 more than yours, before about $40,000 in agent fees, closing costs and the move]. The suite costs [$168,000], and you stay [on the street you love].

If nothing changes: [what the clients said happens otherwise, such as "the kids keep sharing a room, and you start looking at houses in the spring"].

Our 2015 book on proposals asks: "What will happen if this project doesn't go ahead?" For an addition the honest answer is usually a move. Ask what a bigger house nearby would cost them, and put their number in "What it's worth": it's the comparison they're making anyway.

3. How we'll build it

The job in stages, with the weeks, the inspections and what the clients decide at each one, then how you run the site while they live there. The first line says why the cheaper route won't do. If you didn't talk about one, delete it.

We talked about [turning the garage into a bedroom instead]. It would cost less, but [you'd lose the garage, and the room would sit at the front of the house, away from the other bedrooms]. So here's the plan: [16] weeks on site once the permit is issued, in six stages.

  1. Before we start ([4 to 8] weeks): [our designer and a structural engineer] draw the plans, we apply for the permit, and you choose your fixtures, tile and finishes [with us at the supplier]. Every choice is made before we break ground, so nothing on site waits for a decision.
  2. Weeks [1 to 3]: site work and foundation. We mark out the addition with you, dig, pour the footings and build the [crawlspace] foundation. The inspector signs off the footings before we pour.
  3. Weeks [4 to 7]: framing, roof and windows. Walls, roof, sheathing, [roofing and siding to match the house], the windows and the outside door. By the end of week [7] the addition is weathertight.
  4. Weeks [8 to 10]: plumbing, electrical, heating and insulation. The bathroom's plumbing, the wiring, lights and outlets, [heating and cooling from your existing system], then insulation. Each inspection is signed off before the walls are closed.
  5. Weeks [11 to 14]: walls and finishes. Drywall, tile, flooring, the closet, the vanity, doors, trim and paint, then your fixtures.
  6. Weeks [15 and 16]: opening into the house and handover. We open the new doorway from [the hallway] behind a dust wall, patch and paint around it, pass the final inspection, and walk the suite with you to list anything to fix. It's fixed before the last invoice.

On site: we work [7:30 a.m. to 4 p.m., Monday to Friday]. [Our site lead's name] is there every working day and is the one person you call. The dumpster sits [in the driveway], and the site is cleaned up at the end of each day.

Every Friday you get a short update with photos: what got done, what's next, and anything we need you to decide. If a date moves, you hear it from us that week, with the reason.

Philip Morgan and Jonathan Stark, in our 2015 book on proposals: "If a project does require firm completion dates, call out your assumptions about what will be required to meet those dates." On an addition those are the permit, the weather and the clients' own choices. Put all three in the schedule.

4. Additions we've built for families like yours

Short proof for whoever wasn't at the site visit: two recent jobs like this one, with the size, the weeks on site and whether they finished on time, three photos of one of them, then a reference and your license. Use real jobs and your own photos, with the owners' permission, or leave this section out.

  • [Past client], [town]: [the job, with numbers, such as "a 380-square-foot primary suite over a crawlspace, 15 weeks on site, finished two days before the date in our proposal"]. [Link to the photos]
  • [Past client], [town]: [the job, with numbers]. [Link to the photos]
The timber frame and roof trusses of a house going up, against a blue sky A finished bedroom with a large bed, a desk and an arched window A finished bathroom with a freestanding tub, an oak double vanity and a glass shower
[Our last addition: the framing, the finished bedroom and the bath. Replace these with photos of your own work.] Photos: Troy Mortier, Clay Banks, GoodLifeConstruction on Unsplash

"[A one-line quote from one of those clients.]" [Name, town]

[Name] is happy to take a call about [their addition], and you can look up our license, [number], on [your state's contractor license board website].

Three photos of one job like theirs, not a portfolio: the stage they worry about and the rooms they want. In Nusii, proposals with images were accepted less often than those without (43% against 56% for the same 31 senders, July to September 2026), though that may say more about the projects than the pictures. Link to the rest of your work.

5. What's included

Draws the line between what the price covers and what it doesn't, says how allowances, changes and surprises are handled, what you need from the clients, and gives your license, insurance and warranty. Most arguments on a building job start with "I thought that was included".

Included

  • Drawings, structural engineering, the building permit and its fees
  • Everything in How we'll build it: labor, materials, equipment and our subcontractors
  • A [$14,000] allowance for the fixtures and finishes you choose: [the tub, shower valve and trim, vanity and top, toilet, light fixtures and tile]
  • Hauling away all construction waste, and a professional clean at the end
  • Our [one-year] warranty on our work, and the manufacturers' warranties passed to you
  • [Lien releases from our subcontractors and main suppliers as they're paid]

Not included

  • Work inside the house beyond the new doorway and the wall around it
  • Lawn, landscaping and fence repair more than [five feet] from the addition
  • [An electrical panel upgrade, if the inspector requires one, priced before we start]
  • Testing for or removing asbestos or lead paint in the existing house
  • Window coverings, furniture and moving your things out of the way

Allowances: if the fixtures you choose cost more than the [$14,000] allowance, you pay the difference; if they cost less, we take it off the last invoice. You see the supplier's receipts.

Changes: anything you ask to change, and anything the inspector requires that isn't in the plans, gets a written change order with its price and how it moves the finish date. We build it only after you've signed it.

What we find: if we find something nobody could see before we dug or opened a wall, like [rock, rotten framing or wiring that isn't to code], we stop that part, show you, and price the fix in writing before we go on.

What we need from you: your fixture and finish choices by [date], access to [the side gate, an outdoor outlet and water], the work area and the room next to it cleared, and an answer within [two working days] when we ask you to decide something.

License and insurance: [state] contractor's license [number], [general liability insurance of $1 million] and workers' compensation for our crew. Certificates before we start.

California's contractor license board lists what a home improvement contract there must say, including who gets the permits, the completion date, your license number and any warranty in writing. Put the same things in the proposal, and the contract that follows holds no surprises.

6. Investment

One fixed price in stages, each invoiced when that stage is finished and inspected, with the deposit and the allowance named in the lines. These are example prices; the table further down shows what this job costs on average in the US.

Drawings, engineering and permit

$9,500

Plans for the [24-by-16-foot] suite, structural engineering, the permit application and its fees. The [$1,000] deposit is due when you sign the contract and counts toward this stage [check your state's limit on deposits]; the rest is invoiced when the permit is issued.

Site work and foundation

$21,000

Layout, digging, footings and the [crawlspace] foundation with drainage. Invoiced when the foundation inspection is signed off.

Framing, roof, windows and exterior

$41,000

Walls, roof, sheathing, [roofing and siding to match the house], [four] windows and the outside door. Invoiced when the addition is weathertight.

Plumbing, electrical, heating and cooling

$29,500

The bathroom's plumbing, the wiring, lights and outlets to code, and [heating and cooling from your existing system]. Invoiced when the rough-in inspections are signed off.

Insulation and drywall

$12,500

Insulation to code, then drywall hung, taped and finished. Invoiced when the drywall is finished.

Interior finishes

$31,000

Tile, flooring, the closet, doors, trim and paint, and installing your fixtures. Invoiced when the finishes are done.

Fixtures and finishes allowance

$14,000

The fixtures and finishes you choose, as under Allowances in What's included. Invoiced when they're installed; any difference from the [$14,000] is settled on the last invoice.

Opening into the house and handover

$9,500

The new doorway from [the hallway], patching and painting around it, the final inspection, the walk-through with you and a professional clean. Invoiced after the final inspection, once everything on the walk-through list is fixed.

Total: $168,000

In Nusii, proposals where the client could choose between options were accepted less often than those with one price (40% against 52% for the same 91 senders, July to September 2026). On a building job the allowance does the choosing: one price, and the clients still pick the tile.

7. Next steps

Tells the clients exactly what to do to say yes, what the contract adds, the dates that follow, and when you'll call. No expiry date and no "limited availability".

  1. If the plan works for you, accept and sign this proposal.
  2. Within [two working days] we send you the contract for the same work and price, with the notices [your state] requires. You sign it and pay the [$1,000] deposit.
  3. [Our designer] has the drawings ready by [date], and we apply for the permit that week. Permits in [city] take about [six] weeks.
  4. You choose your fixtures, tile and finishes with us by [date], so nothing on site waits for a delivery.
  5. We start on site on [date], once the permit is issued, and you get the first Friday update that week.

I'll call you on [a day three to five days from now] to answer any questions. If you'd rather go through it together at the house, tell me a time that suits you both.

Half the proposals accepted in Nusii were accepted within a day of the client's first look (50.3%, July to September 2026). An addition is a bigger decision than most: a couple talks it over and sorts out the money. Our 2015 book suggests a call three to five days after you send it; offer to go through it at their kitchen table.

A construction proposal example, filled in

Two sections of the template above with a client's words in the brackets, so you can see how it reads when it's done: a home addition by a general contractor. The clients, a couple with two children in a 1960s ranch house, are made up, and so are their numbers.

Your new primary suite, built and ready to move into by June 2027

What we heard

  • You said the kids share a room, and you two have the smallest bedroom in the house. We'll build a primary suite of your own at the back, so each child gets a room.
  • You said you can't live with months of dust and workers in the kitchen. We'll build the addition from the outside and open the wall into the house only once it's weathertight, behind a sealed dust wall, in the last two weeks.
  • You said the last contractor's price went up every week. We'll hold one fixed price. Only two things change it: a change you ask for and sign, and something hidden in the ground or the walls, which we show you and price in writing before we touch it.

What we measured: a flat back yard with 32 feet to the property line, a 1960s ranch house on a crawlspace, a 100-amp electrical panel, and the gas and sewer lines along the north side.

What stays: the oak tree, the patio and the kitchen.

What success looks like: you sleep in the new suite by June 1, 2027, every inspection is signed off, and the final price is $168,000 plus only the changes you signed.

What it's worth: you told us a four-bedroom house in the same school district costs about $150,000 more than yours, before about $40,000 in agent fees, closing costs and the move. The suite costs $168,000, and you stay on the street you love.

If nothing changes: the kids keep sharing a room, and you start looking at houses in the spring.

Investment

Drawings, engineering and permit

$9,500

Site work and foundation

$21,000

Framing, roof, windows and exterior

$41,000

Plumbing, electrical, heating and cooling

$29,500

Insulation and drywall

$12,500

Interior finishes

$31,000

Fixtures and finishes allowance

$14,000

Opening into the house and handover

$9,500

Total: $168,000

How to write a construction proposal, step by step

Six steps, from the site visit to the follow-up call. The template above already follows them; here's why each one matters.

  1. Walk the site with the clients before you price anything

    Measure, look at the panel, the slope, the access and what's under the house, and ask why they want to build now instead of moving. Write their answers down in their words: they become "What we heard". Our 10 questions for the first client call work at a kitchen table too.

  2. Agree on a budget range before you write

    A $168,000 proposal to people who had $90,000 in mind wastes a week of your evenings. Our 2015 book's question works on a building job: "What budget range did you have in mind? A ballpark figure is fine." If they're borrowing, the lender's number is their budget. More on asking about the budget.

  3. Price it in stages the clients can picture

    Get your subcontractors' numbers first, then group the work into the stages the clients will see happen: foundation, framing, the trades, finishes, handover. Eight lines they understand beat two hundred they can pick apart. What they haven't chosen yet, like the tile and the fixtures, goes in as an allowance.

  4. Give one price and tie each payment to finished work

    One fixed price, paid stage by stage as each one is finished and inspected. In Nusii, proposals with options for the client to choose between were accepted less often than those with one price (40.4% against 51.7% for the same 91 accounts, July to September 2026). Check your state's rules on deposits: in California, a home improvement deposit can't be more than $1,000 or 10% of the price, whichever is less.

  5. Write down what isn’t included and how changes work

    Kai Davis, in our 2015 book, keeps a "Risks and Assumptions" section in every proposal. On a building job that's what's not included, the allowances, change orders and what happens if you find rot behind a wall. If the price is too high, the book's advice holds: "Reduce the scope before you reduce your price."

  6. Send it as a link, walk them through it, then call

    Send it with a short email (there's one below) and offer to go through it together, as Marcus Blankenship does with a "proposal walkthrough" in our 2015 book. Call when you said you would, three to five days later. In Nusii you see when it was opened, so you know whether they've read it before you pick up the phone.

    If two weeks pass in silence, send one last line, from Blair Enns via the same book: "I haven't heard back from you on the addition, so I'm going to assume you've gone in a different direction or your priorities have changed."

See it as your client will

Every page of the PDF, printed by Nusii. Sent as a link, it's one scrolling page on any device: your client accepts with one button and signs with their name.

Open the live preview

The template in Nusii, the way your client will see it. It opens in a new tab.

What a home addition costs

The template's example, $168,000 for a 24-by-16-foot primary suite over a crawlspace, sits just under JLC's 2025 national average for the same job, $170,517. The split across the eight stages is ours, to show the shape; your subcontractors' quotes set yours. Before you name a price, find out what the clients have in mind: how eight freelancers and agency owners ask about the budget.

What Price
Primary suite addition, midrange $170,517 24 by 16 feet over a crawlspace, with a walk-in closet and a full bathroom; national average Journal of Light Construction
Primary suite addition, upscale $351,613 national average Journal of Light Construction
Bathroom addition, midrange $60,645 6 by 8 feet over a crawlspace; national average Journal of Light Construction
Bathroom addition, upscale $111,255 national average Journal of Light Construction
Accessory dwelling unit $166,406 national average Journal of Light Construction
What a midrange primary suite adds at resale $55,097 32% of its cost, from a survey of real estate agents Journal of Light Construction

Sources: Journal of Light Construction, 2025 Cost vs Value Report, national averages. These are national averages for the job exactly as JLC specifies it, built from cost data for each market. Prices in your area can be far off them: price from your own subcontractors' quotes, not from a table.

How often proposals got a yes, by price

These are all proposals, not only construction ones. A home addition sits in the top bands, where proposals were accepted less often than small ones: one more reason to agree on the budget at the site visit, before you write. From 1,713 proposals first sent with Nusii, July to September 2026.

Under $1,000
67.1%
$1,000 to $5,000
50.7%
$5,000 to $15,000
48.9%
$15,000 to $50,000
36.1%
Over $50,000
33.3%

Share accepted, by the total the client saw. Bigger proposals are bigger decisions, so this shows what happened, not that a lower price would win. Method: The State of Proposals 2026.

The email to send it with

The proposal does the explaining, so the email only has to get it opened and say when you'll call. Leave the price out, so they read the plan before they judge the number, and send it to both homeowners. In Nusii this goes in the Send Proposal window, and you can save it as your template for next time.

Subject: [Your primary suite: the plan, the schedule and the price]

Hi [first name],

Thanks for walking me through the house on [day of the site visit]. Here's the proposal for [your new primary suite]: [link].

In short: [16] weeks on site once the permit is issued, one fixed price, and you pay as each stage is finished and inspected.

You can accept it right on the page. If you'd like to go through it together at the house, reply with a time that suits you both.

I'll call you on [a day three to five days from now] to answer any questions.

[Your name]

What happens after you send it

Of 8,319 proposals first sent with Nusii from November 2025 to October 2026, all industries, 49.9% were accepted, with a median of 2.9 days to a yes.

49.9%
were accepted
48 minutes
median time to the client's first look
2.9 days
median time to a yes
66.5%
of the yeses came within a week

Clients rarely say no. Of all proposals sent with Nusii from July to September 2026, 6.5% were rejected and 45.2% got no answer either way. Silence is the usual no, so a follow-up is worth sending.

Send it again, then call. Proposals sent a second time, more than an hour after the first send, were accepted 59.8% of the time, against 47.9%, for the same 100 accounts (July to September 2026). That's a correlation, not proof: an interested client may be why they were sent again. In Nusii you see when the proposal was opened, so you can call once both of them have had a chance to read it.

More numbers and the method: The State of Proposals 2026.

Get the Word and PDF files

The same template as a Word file you can edit (it opens in Google Docs too) and a PDF printed by Nusii. We'll email you both, plus a few emails with proposal tips. Unsubscribe any time.

Or send it with Nusii

This template is in the gallery of every Nusii account. Send it as a link: you get an email when your client opens it, and they accept and sign online, on any device.

Just this week, I sent a large proposal to a new client who said, ‘I don’t know what proposal software you’re using, but this is amazing and so easy to review.’

Sophie Haines
Sophie Haines
Account Executive, Buildout

I have no hesitation in recommending Nusii and the team behind it and have been using it for almost 8 years without cause for any complaint, only praise.

Julian Ghail
Julian Ghail
Director, RFID Cloaked
Start your free trial

14-day trial · 60-day money-back guarantee

Questions about construction proposals

What is a construction proposal?

A document a contractor sends after a site visit to win a building job: what the client needs, how you’ll build it and when, what’s included and what isn’t, the price and how it’s paid, and how to say yes. It’s written to win the work in plain words. The contract, with the legal terms, usually follows once the client accepts.

What should a construction proposal include?

What the client told you and what you measured, the work in stages with a schedule, what’s included and what isn’t, allowances, how changes and hidden problems are handled, your license, insurance and warranty, one price with its payment schedule, and the next steps. That’s the seven sections of the template on this page.

How do you write a construction proposal?

Visit the site, agree on a budget range, then write it from the client’s side: their problem in their words, your plan in stages, one fixed price paid as the work is done, and what happens next. The steps above go through it in order, and the template follows them.

What’s the difference between a construction proposal and a bid?

A bid is usually a price for work someone else has already defined, often on the owner’s or the general contractor’s own form, and it’s compared mostly on price. A proposal also says what you heard, how you’ll build it and what’s included, which is how you win a job that isn’t decided on price alone. If the client sent a bid form, fill it in and attach your proposal.

Is a construction proposal a contract?

No. The proposal wins the job; the contract sets the legal terms. In California, for example, any home improvement job over $500 needs a written contract with specific notices. This template covers the scope, the price, the payments, changes and the warranty in plain words, but it isn’t legal advice: send the contract your state requires once the clients accept.

How much deposit can a contractor ask for?

It depends on the state. In California the down payment on a home improvement job can’t be more than $1,000 or 10% of the contract price, whichever is less, and later payments can’t run ahead of the work done, according to the Contractors State License Board. Check your own state’s rule before you fill in the deposit.

How much does a home addition cost?

JLC’s 2025 Cost vs Value report puts a midrange 24-by-16-foot primary suite addition at $170,517 on national average, and a 6-by-8-foot bathroom addition at $60,645. Local prices vary a lot, so price from your subcontractors’ quotes. This template uses $168,000 as an example price.

What is an allowance in a construction proposal?

An amount inside the price for things the client hasn’t chosen yet, like fixtures and tile. If they choose something more expensive, they pay the difference; if cheaper, they get it back. It lets you give one fixed price before every choice is made.

How should change orders work?

In writing and before the work: what changes, what it costs and how it moves the finish date, signed by the client. That covers changes the client asks for, what the inspector requires and what you find behind a wall. The template says so in What’s included, so the first change order isn’t a surprise.

Can I use this template for commercial construction?

Yes. Swap the homeowners for the business owner or facilities manager, the primary suite for the build-out, and the move they’re avoiding for what a late opening costs them in rent and sales. Commercial jobs often hold back part of each payment until the end (retainage) and ask for insurance certificates naming the owner: add both to What’s included.

Is this a general contractor proposal template?

Yes. It’s written for a general contractor or builder who runs the whole job, from the permit to the final inspection, with their own crew and subcontractors. The stages, the allowances and the change orders are the parts a homeowner hiring one company for everything needs to see.

Is this construction proposal template free in Word and PDF?

Yes. Read the whole template on this page, or leave your email to get it as a Word file and a PDF. To send it as an online proposal your clients can accept and sign, use it in Nusii.

Can my client accept and sign the proposal online?

Yes, if you send it as an online proposal. In Nusii, your client opens a link, accepts with one button and signs with their typed name, on any device, and you get an email when they do. The Word file and the PDF need signing the old way.